Wednesday, October 31, 2007

Foundation Construction - 8/1/07 thru 10/4/07

Cut footer for basement
8/1/07

Footer had several stepdowns...5 foot elevation difference from back to front of basement.
8-6-07


Basement footer complete
8/6/07


Concrete blocks delivered
8/10/07


First block laid
8/27/07


First of 17 days of block work...very slow with only a two man crew.
8/27/07


Onward and upward
9/11/07


Two of the basement walls topped out at 21 courses.
9/11/07


Upper level of house to be on a crawlspace.
9/11/07


Pumper truck used to place concrete in upper level footers.
9/20/07

Pumper truck had a long reach
9/20/07

Placing concrete in formwork at transition from basement to crawlspace.
9/20/07


Upper level crawlspace footers complete
9/25/07


Only one course of blocks needed for upper level crawlspace.
10/4/07