Framing - 10/15/07 thru 10/31/07

Framing began in the basement with a bathroom, utility room and mechanical room.
10/15/07

Floor joists installed over crawlspace.
10/16/07

Floor decking installed over crawlspace.
10/16/07


Floor joists and decking installed over basement.
10/17/07


First wall raised
10/18/07

First wall up...way up!
10/18/07

First floor walls up
10/21/07

Raising tub/shower for second floor
10/25/07


Second floor walls going up
10/25/07


Second floor up and starting on roof
10/29/07


It's a tall one!
10/29/07

Back side of house on a solid rock foundation.
10/29/07


Back side of house
10/29/07

Second floor roof beams complete
10/31/07